"The outage affected 9000 servers and 7500 customers. "This evening at 4:55pm CDT in our H1 data center, electrical gear shorted, creating an explosion and fire that knocked down three walls surrounding our electrical equipment room. Thankfully, no one was injured. In addition, no customer servers were damaged or lost," Kevin Hazard said during his update post on the forums over at The Planet. "We have just been allowed into the building to physically inspect the damage. Early indications are that the short was in a high-volume wire conduit. We were not allowed to activate our backup generator plan based on instructions from the fire department.""
Crazy place to have an explosion....
You're in Easy Mode. If you prefer, you can use XHTML Mode instead. |